Nevis Premier welcomes Phase II of geothermal development project

 

(Seated L-R) General Manager of West Indies Power Nevis Mr. Rawlinson Isaac, Chief Executive Officer of West Indies Power Nevis Mr. Kerry McDonald, Premier and Minister of Finance in the Nevis Island Administration Hon. Joseph Parry and Permanent Secretary in the Ministry of Finance Mr. Laurie Lawrence. (Standing L-R) Subsurface Well Manager of West Indies Power Mr. Johan Sydow, President of Just Hot Resources Mr. James Hanson, Senior Project Engineer of Power Engineers Mr. Chun Chin, Geothermal Programme Director of TurboCare Mr. Donald Leger, Business Development/Industrial Projects Manager of White Construction Mr. James Foster, Director of Structured Finance of Scotiabank, International Corporate and Commercial Banking Mr. Richard McCorkindale and Senior Industrial Estimator of White Construction Mr. Ruben Olivas

CHARLESTOWN NEVIS (November 17, 2010) — Premier of Nevis and Minister of Finance in the Nevis Island Administration (NIA) Hon. Joseph Parry, welcomed the news of Phase II, the next major stage of geothermal development which is slated to commence in earnest in late January early February 2011. He said the progress would mean a lot to the government of Nevis.

 

A visibly elated Premier Parry told the Department of Information on Tuesday on the heels of a meeting at his Bath Hotel Office with geothermal developers West Indies Power and an advance team of geothermal plant designers, engineers and budget planners involved in the construction of the geothermal plant at Spring Hill along with a representative from the project’s financiers, that the NIA had placed its bets on geothermal development in the interest of the people of Nevis and Phase II of the project meant everything.

 

According to the information he had received from West Indies Power Executives, drilling geothermal holes for the 10megawatt power plant at Spring Hill, would commence in the latter part of January or early February next year and onsite work on the actual geothermal power plant would begin in March. Financing for the project had also been finalised.

 

“This stage of the project means everything to the Nevis Island Administration. We have placed our bets on the development of geothermal on the island as a means to diversify the economy and to provide cheaper and consistent electricity; to provide electricity for St. Kitts and possibly beyond St. Kitts…

 

“The government of Puerto Rico is interested in the geothermal energy if we are ever able to supply geothermal energy to them. So it means everything – jobs, more cascading industries, other industries and furthermore to make Nevis the first green government in the western hemisphere and eventually to make St. Kitts and Nevis the first green nation in the western hemisphere,” he said.

 

Mr. Parry, who was accompanied by Permanent Secretary in the Ministry of Finance Mr. Laurie Lawrence, pointed to the involvement of United States Secretary of State Mrs. Hilary Clinton and her husband Mr. Bill Clinton’s push for geothermal energy development in the region.

 

“I believe that the American government will be happy to be associated with that and the entire region because what it will do basically is to confirm Nevis as a leader.

 

“We have the first wind farm in the OECS, we have the water project which is one of the first of its type in the OECS and with the geothermal energy we will not only be a leader but we will be an example to the rest of the Caribbean and CARICOM areas, that you don’t sit around and wait for grants and handouts but you can develop your resources for the benefit of your people,” he said.

 

The Premier said the announcement of the start date for Phase II of the geothermal development project on Nevis had come when oil prices on the world market seem to be on the rise due to circumstances occurring in the United States of America.

 

He said as a result Nevis like other islands of the Caribbean were subject to the vagaries of the movement of the US dollar and the Nevis Island Administration wanted to eliminate that because the island’s economy could not withstand with those shocks which were coming more frequently over the past few years.

 

“We don’t know where the situation will end. We certainly don’t want to be once again at a point where the price of oil is being sold for US$150 a barrel and that would be just too much for the consumers here who use electricity on the island of Nevis. So we need to have this project done and we need to have it done fast,” he said.

 

Notwithstanding, in an invited response with regard to recognition Nevis continued to receive for its bold and pioneering decision to develop its renewable energy resources, Mr. Parry who is also the Minister responsible for Tourism said, worldwide recognition was part of the strategy as well.

 

He reminded that tourism was another of the island’s top priorities and if the name of Nevis became known worldwide, that’s the way the NIA wanted it to be.

 

“It’s good for us in terms of tourism, it’s good for us in terms of other investment because businesspeople know and they would look at their options and see if it makes sense to have anything to do with Nevis.

 

“Of course we know we are small, we have a small population, we have a small land mass [and] we don’t expect people are going to come here in great numbers. If they do we are in trouble but we certainly want some quality people to come and invest on the island and it means a lot for our treasury and our employment situation,” he said.

 

The team who met with Mr. Parry was led by Chief Executive Officer of West Indies Power Nevis Ltd. Mr. Kerry McDonald, the company’s General Manager Mr. Rawlinson Isaac and newly appointed Subsurfaces Wells Manager Mr. Johan Sydow.

 

The advance team comprised of White Construction’s Senior Industrial Estimator Mr. Ruben Olivas and Business Development/Industrial Projects Manager Mr. James Foster. That company will be responsible for installation of the geothermal plant and is the engineer procurement and construction contractor and its associates Power Engineers, was represented by Senior Project Engineer Mr. Chun Chin

 

TurboCare a company owned by Siemens who are constructing the plant, was represented by Geothermal Programme Director Mr. Donald Leger. President of Just Hot Resources Mr. James Hanson represented his company that will drill the new wells at Spring Hill and Director of Structured Finance of Scotiabank, International Corporate and Commercial Banking Mr. Richard McCorkindale.